Work Includes engineering calculation and preparation of the work shop drawing of the electrical and low current system installations.
Work shop drawing: a total of 450 no. of sheets have been produced and Approved for this project.
This includes several buildings.
- Emergency Building
- Inpatient building.
- Outpatient building.
- Residence building.
- Administration building.
- Electromechanical building.
- main circulation spin.
- Substation 12.0 MVA.
- Site layout
Sector |
EgyptBuildings & Commercial Sector |
Location |
Nasr City, Cairo, Egypt |
Owner |
Al Azhar University |
Architect |
Shafie – Sherif bureau. (Prof. Dr. Zakia shafie. & Dr. Ahmed sherif) |
Main Consultant |
Shaker consultancy group |
Description |
700 bed hospital |